Suzhou high tech Zone, the first use of "maglev" drive technology of parking systems. Garage covers an area of about 1000 square meters, about 20 meters high, is divided into eight layers. The entire garage has been completed equipment installation and commissioning work.
The driver just needs to drive the car to the garage entrance and get off the bus. The computer will automatically find the nearest parking space, and the vehicle through translation, ascension, and finally parked into the warehouse. The whole parking process is only 30 seconds fastest."Maglev" stereo garage project manager Luo Qiang: "our own verification of noise is only 35 decibels, other traditional parking noise will be more than 70 decibels."
In some residential areas, downtown is also a great advantage. In addition, the direct drive technology, so special maintenance, our design life is more than more than 10 years."
It is understood that the "maglev" stereo garage can reach up to 25 layers, and all parking spaces only need a set of transmission systems and truly maximize the use of space.
2017年10月15日星期日
2017年8月22日星期二
Suzhou province Shishan road at the end of August to achieve P+R parking lot
At the intersection of Riverside Road, Shishan Road, Riverside Road parking lot of civil air defense projects have been completed 70% of the continuous underground wall construction, is expected to be completed by the end of September 2019, with nearly 400 parking spaces. The project will be connected to Metro Line 3 Yushan Road stations so that drivers can change trains to the subway.
In addition, at the end of the first bus station Yuen Road, the construction of "laser navigation + comb exchange type parking lot, is expected by the end of August to complete the installation and commissioning.
Originally, this more than 3600 square meters of land just Yuen bus parking lot, after the transformation, the same area, in addition to the end of the first bus station, and added a seven on the ground floor, underground parking, 260 parking spaces available for the motor vehicle.
Parking System previously is used in platen automatic parking guidance system, and comb type now save a traverse equipment through the carrier and base on the cross exchange mechanism comb the position of the vehicle, safe and fast, the whole process of taking the car time average is 85 seconds.
In addition, at the end of the first bus station Yuen Road, the construction of "laser navigation + comb exchange type parking lot, is expected by the end of August to complete the installation and commissioning.
Originally, this more than 3600 square meters of land just Yuen bus parking lot, after the transformation, the same area, in addition to the end of the first bus station, and added a seven on the ground floor, underground parking, 260 parking spaces available for the motor vehicle.
Parking System previously is used in platen automatic parking guidance system, and comb type now save a traverse equipment through the carrier and base on the cross exchange mechanism comb the position of the vehicle, safe and fast, the whole process of taking the car time average is 85 seconds.